[MW:11051] GRE pipings

Dear Experts,
 
          I'm working as TPI and representing ADNOC and my contractor who is doing GRE piping works. some of the works completed and I have checked them and found ok.
 
      Now GRE piping installed and the pipings needs to be hydro tested. But I haven't been provided any documents regarding the procedures like method os statement for the hydro testing. I dont know even what pressure is? what is the holding time? no details were given in the drawing. How many pressure gauges to be used? where it is needed recorder etc,
NO QCP/ITP/hydro testing procedures.
 
Can anyone explain me how to sort out this problem? And what are the documents shoul I ask prior to this job?if possible some procedures and stds can be sent it to me.
 
Thanks in advance

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...