Dear Experts ,
-- due to time concentrate we are unable to do the RT as we need to arrange the RT crew and ID's process for site access ...........
as per drawing 5% RT is required .
we can perform hydro of tie in joints ?
can you please advise for the reference from ASME B31.3 ?
Best Regards,
Zafar Iqbal