[MW:32560] ASME B31.3 process piping Hydro in Lieu of RT

Dear Experts ,
due to time concentrate we are unable to do the RT as we need to arrange the RT crew and ID's process for site access  ...........

as per drawing 5% RT is required .

we can perform hydro of tie in joints ? 

can you please advise for the reference from ASME B31.3  ? 



Best Regards,
Zafar Iqbal 
00966544639978 

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAP9k9XcM6-QrnGrGm5%3DBN46HRJx_k6DKiaPBs6Pbpjw033JPSA%40mail.gmail.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...