Use any ni base electrode like ENiCrMo3 for this weld, before welding do backing at 250 deg cel min for 30 min then maintain 150 deg cel during welding interpass must be contoll at 300 deg cel max
After welding cover with blanket to reach room temp at uniform rate of cooling
--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
Subscribe to:
Post Comments (Atom)
Re: [MW:35507] WPS for Furnace PWHT
As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...