ASME B31.3 refers ASME Sec.IX for WPS/PQR qualification. PWHT Soak time after Repair will be considered during original PQR qualification and when Charpy Impact tests are required, below snap shot of ASME Sec.IX applies. Normally in Pipe Mill, MPQ (Manufacturer Procedure Qualification) with welding & Heat Treatment will be performed including repair PWHT cycles during pipe production. Thanks & Regards J.Gerald Jayakumar 0091-8838619635 On Thursday, 29 January 2026 at 08:52:28 am IST, Babur Khan <mbabur.bwp@gmail.com> wrote: Greetings, Thank you for your kind response. In pur PQR, soaking time for repairs Welding not considered. Muhammad Babur Khan Sent from my iPhone On 28 Jan 2026, at 8:48 AM, 'james gerald' via Materials & Welding ...