Re: [MW:33099] Pig launcher

Dear Mezrar,

It depends if Client has any Pigging Specification. In one of my project we were going to design as per B31.3 due to piping connected was also B31.3. but later we found that the Client Spec was saying about ASME Sec VIII Div. 2 hence we had to change the design code.

Also the pig receiver design code has to be designed as per the connecting piping code which is by Piping.

Sent from RediffmailNG on Android




From: Benaouda Mezrar <mezrarbenaouda4@gmail.com>
Sent: Tue, 31 May 2022 08:50:57 GMT+0530
To: Materials & Welding <materials-welding@googlegroups.com>
Subject: [MW:33098] Pig launcher

Dear experts kindly guide me

in which code i can find the acceptance criteria for the construction of pig launcher
and what is the desing code used (ASME B31.8 or ASME ASME-8)

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https:roups.google.com/d/msgid/materials-welding/9ac05358-95d4-40ca-b12d-51d014da78b9n@googlegroups.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/1653968360.S.10049.autosave.drafts.1653968606.27970%40webmail.rediffmail.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...