Re: [MW:33058] channels and bonnets with six or more tube passes

Screenshot 2022-05-04 095405.jpg
On Tuesday, 5 April 2022 at 16:43:54 UTC+5:30 MW wrote:
since it is 6 pass, required

On Tue, 5 Apr 2022 at 16:36, 'manohar matcha' via Materials & Welding <material...@googlegroups.com> wrote:
Please look into the attachment and advise that pwht is applicable for these channels as per API 660 clause 9.6.9 (a) or not?
Both channels are belongs to one HE.
Regards,
Manohar.

ClauseFrom: Raghuram Bathula <raghura...@gmail.com>
Sent: Tue, 05 Apr 2022 15:37:49
To: Materials-Welding <material...@googlegroups.com>
Subject: Re: [MW:33030] channels and bonnets with six or more tube passes
 
it is from one end of HE to another end is consider as 1 pass (not individual channel)
 
On Tue, 5 Apr 2022 at 15:22, 'manohar matcha' via Materials & Welding <material...@googlegroups.com> wrote:
Dear Group Members,

Please share your opinion/interpretation on API 660 Clause 9.6.9 (a)


 
Tube passes to be considered for individual channel or both channels (if Exchanger is having 2 channels)?
 
in other words:
Individual Channel passes to be considered or cumulative passes for both channels to be considered..?

Regards,
Manohar.

 

 

--

 

--

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/221430c3-4bcd-4a65-948d-6f2b3519bf3fn%40googlegroups.com.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

[MW:36169] Cold Bending Qualification

Dear Experts,  Can anyone share the inspection requirements or a qualification procedure for cold bending? Our client spec states only the requirements for induction bending and would like to know your opinion on the cold bend inspection requirements. The code of construction is B31.3, Max. 5D bends, A106 SS 316L.  Thanks in Advance. -- https://materials-welding.blogspot.com/ https://www.linkedin.com/groups/122787 --- You received this message because you are subscribed to the Google Groups "Materials & Welding" group. To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com . To view this discussion visit https://groups.google.com/d/msgid/materials-welding/1be61cc3-e9c9-4a5f-834d-e8485e248432n%40googlegroups.com .

[MW:30043] Weep hole

If weep hole is not provided in dummy pipe before welding What will happen??? -- https://materials-welding.blogspot.com/ https://www.linkedin.com/groups/122787 --- You received this message because you are subscribed to the Google Groups "Materials & Welding" group. To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com . To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/da251ee6-fa7f-4851-b876-cdb3834ae341%40googlegroups.com .