Once the welded joint has cooled and radiographic testing (RT) is accepted, hydrotesting may proceed. Except in cases involving special alloys or stress relieving (SR), a waiting period is required."
On Mon, Jan 19, 2026 at 9:19 PM Mahmood Alhinai <mahmood.m.alhinai@gmail.com> wrote:
Dear expert,--Kindly what is minimum time limit between completion of welding and the hydrotest?ThanksMahmood
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CANV5n6iM1bqGdmtzFU4C6dsJZiNnOFpT%3DM3KUq-P1UA%2B1CS7yQ%40mail.gmail.com.
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CAE12Qq7g%3DS_XGOy%2B01WygoCgKTOzTp6TvutTqvCB2vE0Qx%2BJfA%40mail.gmail.com.
Comments