Re: [MW:35940] PWHT for Piping weld joint | heating & cooling rate

Chart is ok. It's meeting code. One more clause, in 4.5meter long , more than 40°c temperature variations also not acceptable.


From: materials-welding@googlegroups.com <materials-welding@googlegroups.com> on behalf of Srinivas Gundala <srinivasrao.gundala@gmail.com>
Sent: Wednesday, December 31, 2025 4:56:22 PM
To: materials-welding@googlegroups.com <materials-welding@googlegroups.com>
Subject: Re: [MW:35939] PWHT for Piping weld joint | heating & cooling rate
 

Dear Hai,

As you confirmed, overall, the PWHT cycle appears satisfactory, meaning that the work was completed according to the approved WPS and within the target temperature achieved, the holding time was completed, and temperature stability was maintained. However, a concern is that local fluctuations were observed in the heating phase above 315°C, which we address below.

As I understood, two PWHT charts were provided, referred to here as Chart A and Chart B for clarity.

  • Chart A: Thermocouple TC-1 (Blue) deviated briefly from its normal trend during the heating stage at approximately 590°C and rejoined the main curve at around 620°C.

  • Chart B: Thermocouple TC-1 (Blue) showed a similar brief deviation during the cooling stage at approximately 590°C and rejoined the main curve at around 520°C.

These fluctuations are considered acceptable based on the following technical rationale:

It is important to note that a longer chart time corresponds to a lower heating/cooling rate, while a shorter chart time corresponds to a higher rate. In Chart A, the deviated TC-1 (Blue) traveled above TC-2 (Green) and required a longer duration to rejoin its original path, indicating that the effective heating rate remained below the maximum allowable limit of 335°C/hr. Therefore, this deviation does not represent a violation of para. 331.1.4 and is acceptable.

The same principle applies to Chart B during the cooling stage. Had TC-1 deviated below TC-2, it would have indicated a faster cooling rate and could have raised concerns regarding compliance. Since this is not the case, the observed fluctuation is acceptable.

I trust the above explanation clarifies the observations and acceptance rationale. 

Suggestions or additional comments from other experts are also welcome.



On Wed, Dec 31, 2025 at 11:09 AM Lê Đình Hải <dinhhaibkdn@gmail.com> wrote:

Dear Experts,

Please help review and advise on the acceptability of the attached PWHT record against ASME B31.3 clause 331.1.4 (Heating and Cooling).

From the chart, the overall PWHT cycle appears satisfactory (target/hold achieved and stable). However, there is one localized segment during the HEATING stage (T > 315°C) where the temperature ramp is steep and the heating rate appears to exceed 335°C/h (local/short-duration excursion). All other portions of the cycle look compliant.

Could you please advise:

  1. Whether this single local heating-rate exceedance can be accepted as-is (engineering disposition/justification), or

  2. If not acceptable, recommended corrective actions (e.g., re-PWHT, additional NDE/metallurgical evaluation, etc.).



Best Regards.
-------------------------------------------------------------------
Name :        Le Dinh Hai (Mr Hai)
Mobile :      Vietnam: +8497 397 1597
Email :        Dinhhaibkdn@gmail.com

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CAAAR47KZPTTMs4Ay7Wky8wAGGWUmSvw12tdqU9iPVApSc9SD7A%40mail.gmail.com.


--
Thanks & Regards,
 
Srinivasrao.Gundala,

Please consider your environmental responsibility: before printing this e-mail, ask yourself whether you need a hard copy!

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/CACn7QWU8TX_07gA69q9RW%3D%2BpJ8vpyyeFW4VisdoTaeYRTxGhHw%40mail.gmail.com.

Comments

Popular posts from this blog

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...