This type of situation is most of the time faced by welding and quality engineers. For this reason quality assurance activities are performed prior to product realization. In this process basically all the documents are properly reviewed  and ensured for compliance for client requirements. we must review the documents - Technical/construction specification(API 650), client specification, client additional requirements and/or any other documents. based on these documents the quality Assurance/control plan is required to be prepared and subsequently approved from clients. once this QAP/QCP approved, further requirement shall be considered as additional requirement.

Being manufacturer,you may proceed in this way

1. if you realize this is impractical at this moment, you should request for non feasible activities at this moment.

2.perform the welding procedure qualification based for critical welding parement and show the results of hardness on test coupon.based on these results request for acceptance of production weld quality  and subsequently revise the PQR/WPS if required.
 
3. If feasible, and time permits, cost calculation shall be performed and  submit cost implication and subsequent time constraints.


Regards

Rishikesh kumar
Global Technical Support|Business Development|Lead Auditor|QA&QC|Welding| Pipe Mills|Steel Plants|Metallurgist

On Mon, Jul 26, 2021 at 9:37 AM Noel Tanilon <noel.tanilon@aboitiz.com> wrote:
Our Client is requesting hardness testing as mentioned in the equipment welding specification, where it stated the hardness test to be carried out on the following area for equipment which include tanks: 1. On Circumferential seam (some percentage) 2. Longitude seam (some percentage) 3. All temporary weld made and remove (100%) All the above requirements are so impractical to us since we are fabricating/erecting atmospheric tank (large diameters too). The amount of temporary weld (for erection purpose) are tremendous i.e. thousands for each crude oil storage tanks and hundreds on the miscellaneous tanks. The hardness test was carried out during the qualification of Welding Procedure Qualification and it meets the hardness value requirement. And there are no requirements for hardness tests as per API 650. I believe that it is meant for pressure vessel tanks only, but OWNER insists on the test since it is stated in the specification. Any comment on this client requirement? Please help.

Regards,

Noel
Noel C. Tanilon Jr
QA/QC Supervisor
Aboitiz Construction, Inc.
t 63 32 411 1800
m +63 917 849 8183
The information contained in this email message is intended for use only by the individual or entity to which it is addressed, and such information may be privileged, confidential and/or proprietary, and protected under applicable laws. 

Read about the full Aboitiz Disclaimer ( http://www.aboitiz.com/disclaimer)

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CANff5sX-CKUrYid-4at6bYtKNN0SFLrsg%2Bw3kKfWK-uV4RdkEw%40mail.gmail.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAEXs1Kqb3NpqJRe6x_iVpFwrWES7VKk%2BxyOoiacf0cg0t9AQ1Q%40mail.gmail.com.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...