Dear Team,
Can anybody suggest for below detail required to fill in MDR of U Stamp Pressure Vessel.
Abbreviations used: NA-Not applicable, MOC-Material of construction, DOE-Degree of examination, RT-Radiographic test, |
|
All Dimensions are in mm, Pressure in Psi(g) (MPa(g)) & Temperature in °F (°C). | |
Hydrotest position is Vertical. | |
Note 1- Nozzle to Shell / Head attachment weld with R.F.Pad as per Fig. UW-16.1(C-1), category 'D',Type No.7, DOE-Visual, | |
RT-None, Joint efficiency-NA | |
Note 2-Nozzle to Head attachment weld with R.F.Pad & intrnal projection as per Fig. UW-16.1(c-1), category 'D', Type No.7, | |
DOE-Visual, RT-None, Joint efficiency-NA | |
Note 3- Nozzle to Head attachment attachment weld as per Fig. UW-16.1(c), category 'D', Type No.7, DOE-Visual, | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
RT-None, Joint efficiency-NA | |
Note 4-Nozzle to shell attachment weld with R.F.Pad as per Fig. UW-16.1(d-1), category 'D',Type No.7, DOE-Visual, | |
RT-None, Joint efficiency-NA | |
Note 5- Nozzle to shell attachment weld as per Fig. UW-16.1(p-2), category 'D', Type No.7, DOE-Visual, RT-None, | |
|
Note 6 - Nozzle to flange attachment weld (Category 'C' weld) - Type No.(1), RT- exempted as per UW-11(a), DOE-Visual, | |
|
Note 7 - Nozzle to flange attachment weld (Category 'C' weld) - Type No.(1), RT-Full as per UW-11(a), DOE-Visual, | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Vessel is under corrosive service hence Inspection Openings are provided as per UG-46(f)(3) & UG-46(g)(1) | |
Vessel is under corrosive service, Drain opening Nozzle N2 (DN 200) is provided as per UG-25(f). | |
Post Forming Heat Treatment (PFHT) exempted for Shell, Head & Manhole Neck as per UG-79 & UCS-79. | |
Post Weld Heat Treatment (PWHT) Exempted as per UW-2, UCS-56. | |
Impact Test is exempted as per- UG-20(f), UCS-66(a) & FIGURE UCS-66M, UCS-66(c)' FIGURE UCS-66 GENERAL NOTE (c), | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
Over pressure protection device is not directly mounted on vessel, Design supply of pressure safety device is not in | |
-- Israr Ahmed Noor Mohammed
+919930308261
--
https://materials-welding.blogspot.com/ https://www.linkedin.com/groups/122787 ---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to
materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit
https://groups.google.com/d/msgid/materials-welding/CAEJozaKcc_b72_fgCBmGhgnyZpq0ZTQYgsg%3D3ABnonfNvy8JMQ%40mail.gmail.com.
No comments:
Post a Comment