Re: [MW:25532] Re: NDE rate in boiler

As per B 31.1, NDE after any Heat treatment

THANKS & BEST REGARDS,
KG.PANDITHAN, IWE,  AWS-CWI, CSWIP 3.1,
CONSULTANT-WELDING & QUALITY
Mobile no: +919940739349

On Wed, Oct 12, 2016 at 10:07 PM, Vishwas Keskar Welding Manager Pune India <vvkeskar123@gmail.com> wrote:
Boxbe This message is eligible for Automatic Cleanup! (vvkeskar123@gmail.com) Add cleanup rule | More info

nps < 4 " = if RT  is taken, the acceptance shall be as per written down RT PROCEDURE 
 
P91 - RT BEFORE AND AFTER BOTH is required as a good eng practice

On Wednesday, October 12, 2016 at 2:30:12 PM UTC+5:30, Tunisian Quality Engineer wrote:
Dear Experts,

  Need your assistance.

Applicable code : ASME sect I
Query : 

1- For Pipes/tubes NPS less than 4" diameter, we need to perform NDE with some ratio, basically according code is not mandatory (table PW-11) : Please inform if any other indication about this issue in code.

2- Could us perform NDE (RT : Volumic) before pwht and complete only by (MT: Surfasic) after pwht for P91 and also for others grades according ASME sect I. What's code requirement for NDE/Pwht.
tat 

--

Thanks and Regards, 

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/0bcbf00a-f553-4d85-8d42-28452834ef0e%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.


--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAJzm4eOOq0pPyEuw_sxTfj3-o_cEBbxDchLduaDmtTLeDRhV4w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...