Saturday, April 13, 2013

Re: [MW:17384] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE


Check/try the following:

As far as consumables are concerned:
  1. Bake (not preheat!) the electrodes, as per the manufacturer's recommended duration.
  2. Ensure the numbers 250, 100 what you have mentioned are not in ° F !! it should be ° C.
  3. If Vac-Pac electrodes are used, do not bake.
  4. Check baking oven, holding oven and quivers are properly calibrated.
  5. Limit the number of rebaking cycles to manufacturer recommendation.
  6. Check the shelf-life of electrodes with the manufacturer.
Others:
  1.  If pre heat is needed, before welding, check the pre heat of base metal is done properly, using approved procedures.
  2. Ensure the cleanliness of the area to be welded.(face, bevel, inside, outside for 1" minimum)
  3. Ensure sufficient wind protection is provided during welding.
  4. Ensure qualified welders are being used.
  5. Ensure approved WPS is being used.
Above mentioned are 'generalized' precautions only. If you provide some more data, it can be analyzed further.

ವಂದನೆಗಳೊಂದಿಗೆ / Best regards,

Nandesh Kumar Arasappa

P.S. : Please don't print this e-mail unless you really need to.


--- On Sat, 13/4/13, jiji lal <jijilalkm@gmail.com> wrote:

From: jiji lal <jijilalkm@gmail.com>
Subject: [MW:17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE
To: materials-welding@googlegroups.com
Date: Saturday, 13 April, 2013, 10:36 AM

SIR,

I'm engaged with welding of API 5LX 80  grade pipeline for regassified LNG transmission . We do  Tie-in method using SMAW+FCAW.
For root pass welding we use E7016-1 electrode after pre heating 250 degree for 2 hr in mother oven and maintain 100 degree in holding oven . during RT interpretation severe hollow bead and porosity observed in root .hence PMC sent almost all joints for repair.now it becomes a serious issue and I think ,the pre heat method was not proper. kindly advice me in this issue.

Mr.Jijilal k .m
qa/qc dept. tecpro ltd.
kochi.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...