Friday, January 4, 2013

Re: [MW:16428] QW407.2 (ASME Sec. IX)

Dear All, 

Thank You very much for your views and explanations. 

I understand that Answer to My Query is "NO". Interpretation IX-07-06 is very clear about it.
I have got also confirmation of this from one of the Senior ASME Authorized Inspector.


Thanks Again

Tariq Hussain 

On Thu, Jan 3, 2013 at 2:50 PM, kannayeram gnanapandithan <kgpandithan@gmail.com> wrote:
If impact is called and also 80%. pl check again
For non impact there is no restriction on temp and time from pqr if ASME material follow relevant construction code otherwise it should as per ur procedure
Pandithan
Welding Consultant


On Thu, Jan 3, 2013 at 1:29 PM, bala murugan <balamuruganqaqc@gmail.com> wrote:
Dear Friend,
                 Nice to meet you. According to ASME Sec 9, QW 407.2
it is clearly mentioned that the PWHT Soaking temp and time which you
had implemented during procedure qualification has to be essentially
equivalent to your production joint.
                 Hope it will be clear to you.

Thanks & Best Regards,
Balamurugan.M,
Sr. QA/QC Engg,
L&T Ecc,
UTKAL REFINERY SITE.

On 1/2/13, Tariq Hussain <tariqhussain632@gmail.com> wrote:
> Dear All,
>
> We need little help from you regarding below query for *ASME Sec. IX
> QW-407.2*
>
> * *
>
> Is it intention of *QW-407.2* to have *Production Welds Soak Temperature
> (Vessel Soak temperature)* exactly same as that of done in PQR test Coupon?
>
>
> Thanks in Advance
>
> Tariq Hussain
>
> --
> To post to this group, send email to materials-welding@googlegroups.com
> To unsubscribe from this group, send email to
> materials-welding+unsubscribe@googlegroups.com
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
>
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>
>
>

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm

The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...