[MW:14426] Tank Clean out door PWHT

Hi, Can any one tell whether I can carry out PWHT of clean out door
welding after erection of first shell course?
We have erected the clean out door section of the shell plate and
completed vertical welding without performing the PWHT. As per API
650, it needs to be completed PWHT regardless of thickness before
assembly(erection).
if that is the case, I have to cut the joint and do the PWHT and
reweld again.Can I do PWHT at site after erection?
If not, any one explain me what is the reason behind it. Why API is
insisting to have PWHT before erection.
Cheers,
Thomas

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...