Wednesday, October 12, 2011

Re: [MW:12660] welding bottom of storage oil tsank

What ever may be the code(API-650/620/653),As Per the distortion concerned at bottom plates,The critical Zone welding(Shell to bottom plate weld) shall be complete prior to the bottom plate welding,practically it should follow to construct a desired  tank bottom with least distortion.
 
 


 
On Tue, Oct 11, 2011 at 8:56 PM, lassaad mokrani <lassaad.mokrani@gmail.com> wrote:
Hi,
If you work as per API 650, so it's most likely to be lap joint welding that could be SAW
Only the circumferential plate shall be with backing strips 2" wide.
The welding mapping, shall be weld defined, from the center up to the side plate to avoid distorsion


2011/10/9 Ahmed Elgendy <eng.aelgendy@yahoo.com>
dear sir ....

could  any  one give me the procedure of welding  the bottom of storage tanks.
for gasoline  tanks  diam.  30 mtr circular tank 



best  regards,,,,
eng. a. elgendy



--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Meilleures salutations

Mokrani Lassaad
00216 20 649 755
http://www.linkedin.com/pub/lassaad-mokrani/16/364/907


















P     Pensez environnement! N'imprimez ce mail que si c'est vraiment nécessaire
Please consider your environmental responsibility before printing this e-mail


This e-mail is confidential and it is intended only for the addressees. Any
review, dissemination, distribution, or copying of this message by persons
or entities other than the intended recipient is prohibited. If you have
received this e-mail in error, kindly notify us immediately by telephone or
e-mail and delete the message from your system. The sender does not accept
liability for any errors or omissions in the contents of this message which
may arise as a result of the e-mail transmission

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.




With Regards,

 

VENKATA BALARAM.INTI | Assistant Manager - QA/QC|

HPCL-Mittal Energy Ltd| Guru Gobind Singh Refinery - Project.|

Phullokhari - Bathinda (PB.) - 151301.| Telefax: 01655 - 241775, Off: 01655 272466

+91-9988885390 |E mailto:venkata.inti@hmel.in

 


--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34820] RE: 34813] Clarification in Rate of heating and cooling.

Hello,   Please see the response below.   Regards.   P. Goswami, P. Eng, IWE.   From: materials-welding@googlegroups.com <materials-weld...