 I need a clarification regarding, Pipe to Flange (Weld Neck). As per my drawing Design As per ASME Sec viii, Joint efficiency - 1, Radiography - Full & PWHT considered. Size of nozzles 80NB, 350NB & 500NB Sch 60. Radiography need to be done for all nozzles. 

--
Thanks & Regards,                                                    
D. Karthick
Ph.No: +91-9787300898

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point