It's much depending on your project quality requirement. As for my experience, after welding there should be pickling and passivation. Of course you won't detect any contamination
In short term on the welded joint.

Rgds,
Mus

Sent by Maxis from my BlackBerry® smartphone


From: sudhakar kuppuswamy <mechsudhakar@gmail.com>
Sender: materials-welding@googlegroups.com
Date: Mon, 19 Sep 2011 23:29:47 +0400
To: <materials-welding@googlegroups.com>
ReplyTo: materials-welding@googlegroups.com
Subject: [MW:12482] pickling and passivation for 316 L SS


Dear Experts,

                       It is mandatory to do pickling and passivation for 316 L SS piping systems, irrespective of services and thickness?  No PWHT is done on  that piping systems, and we have not found any Surface contaminations due to welding.


But our client is insisting us to do Pickling and passivation on welded joints. It is really required?


please share your views.

 

Regards

Sudhakar.k



--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...