Dear All,
How many cycle (Graphs) Permitted in one chart (Graph Papper), In CS
pipe 3 jonits X8" started PWHT in first time and another 3 joints
started after 30minuts at the same graph (with out informing to the
client). it is acceptable as per B31.3?

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire