Tuesday, August 23, 2011

Re: [MW:12301] O-LET WELDING .......

Hamza,
1) As per the manufacture Instruction YOU HAVE TO
FILL THE GROVE.
2) Regarding PWHT you have to follow ASME B .31.3
Branch connection PWHT chart If the throught is more than 38 mm (2 x
19.5 min pwht requirement) you have to do PWHT do the thickness check
during FIT UP Inspection.
3) If you do welding in the shop (or ) in the
site you have to follow the same procedure.
Regards
Mano

2011/8/23, noorudheen hamza <noorucareer@gmail.com>:
> DEAR EXPERTS ......
>
> CAN ANYONE TELL ABOUT O-LET WELDING ....IN MY CASE WELD-O-LET JOINT
> WELDED ONLY 1.5 TIMES THICKNESS OF HEADER PIPE.... NOT COMPLETED FILL-UP
> ALSO .. WHATEVER THEY ARE TELLING ABOUT THIS THEY CAN AVOID PWHT FOR THAT
> JOINT ..... IF IT IS THEY ARE DOING FULL WELD ,UPTO BEVEL OF O-LET ,,AS
> PER THICKNESS OF WELD METAL THEY SHOULD TAKE ..PWHT ..... NW THEY ARE DOING
> 1.5 TIMES THK OF HEADER PIPE IN FABRICATION SHOP ... AND THEY WILL DO
> BALANCE WELDING AT SITE AFTER ERECTION AFTER A LONG TIME .......
>
> MY DOUBT IS, ITS POSSIBLE..?
> WELD HAVE CHANCE TO HAVING CRACK..?
> THERMAL EXPANSION HOW WORK ON IT ..?
> NEED PWHT IF IT IS FULL WELD ..?
> IF THEY ARE WELDING BALACE AFTER ERECTION, NO NEED PWHT ...? WHY..?
>
>
>
> PLEASE GIVE ME HELPFUL INFORMATION ..
> THANK...
>
> NP HAMZA
>
> --
> To post to this group, send email to materials-welding@googlegroups.com
> To unsubscribe from this group, send email to
> materials-welding+unsubscribe@googlegroups.com
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...