Dear All,
 
we are pressure vessel manfacturer  having U - Stamp , we purchase some flanges of carbon steel  which are overlayed, But the supplier did not provide PDR
my question is ,
 
1) Is it required?(Section VIII div. 1 addition 2007)
2)Does the flanges should be stamped "U"

--
With Best Wishes,
 
Imran
 
   

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...