Saturday, July 16, 2011

Re: [MW:11748] weld stop during root pas

Hii ,
 
You can not start directly on next day welding from where you had stopped the welding point ..you need to mantain pre heat(normal) If thicknees less than 1 " and mantian the interpass temprature properly to mantyainheat balance on weld pool,other wise metullurgy errors will be appeared .
Suresh
On Sat, Jul 16, 2011 at 11:59 AM, jagdish patil <jagdishpatil568@gmail.com> wrote:
Dear all,

 I would like to know during welding at root pass stage we stop some reason, but  we can start continue welding on next day without any test is it possible.
if not possible give me the specific reason.


regards,
JAGDISH

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Thanks  & Best Regards,

Suresh

Mobile No: 91-92 92 905 905

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...