Re: [MW:11588] prequalified WPS

Dear ankit ,

prequaified wps is refered for an steel structure with AWS D1.1 based on client approval .This is intended for the non rotating parts welding.In prequalification you have to refer an part 3 in the codes as per the table 3-1TO 3.7 WITH reference drawing 3.3 .
Here no need to qualify an pqr , but the matter it is intended for the static loaded parts .

regards

dinesh 

On Mon, Jul 4, 2011 at 12:30 PM, khatri ankit <nids01dme011@gmail.com> wrote:
Dear All,

I want to the details for preparing Prequalified WPS without testing.

in which circumstances they will prepare? and how it  will be
prepared:

so kindly clear the concept of Prequlified WPS

Regards,

Anki Khatri

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...