Saturday, July 23, 2011

[MW:11877] P-11 with purging

Hi,
I have one ESTABLISHED  WPS for P-11 which is not purged by argon but as per our client specification purging is required for P-11. Can anybody tell me can i use ESTABLISHED WPS for with purged condition.  For that one, what is the criteria  & where it is written in code.
Regards
Pradip

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...