Hello Experts,

Is production test is required as per B31.3 for,
Material: A333 GR6 LTCS PIPE
WPS USED: QUALIFIED AT -50 DEGREE CELCIUS.
CLIENT REQUIREMENT: AS PER B31.3.
--
SANU.K.NAIR
QC INSPECTOR
DAEWOO E & C
ABUDHABI
Ph: 0507464738

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...