Dear Sir,
When project specification and/or your clients requirements demand production test welds than you also have to test the Charpy-V impact properties at required temperatures. This is for verifying that your production achieves the same weld quality as during Procedure Qualification test.
Met vriendelijke groeten / Best Regards
Herman Pieper
Pieper Quality Support & Inspection
Phone: +31 (0)521 380083
Fax: +31 (0)84 7539225
Cell: +31 (0)6 51691215
www.pieper-qsi.nl
Van: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] Namens Sanu Krishnan
Verzonden: maandag 11 juli 2011 10:18
Aan: materials-welding@googlegroups.com
Onderwerp: [MW:11664] Poduction impact test
Dear experts,
Is it Production imact test required for LTCS,upto -50degree C.Already PQR Test qualified in -50 degree C?
--
SANU.K.NAIR
QC INSPECTOR
DAEWOO E & C
ABUDHABI
Ph: 0507464738
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment