[MW:11672] RE: 11664] Production impact test

According to asme code, PTP is required when Impact test is essential.

 

Best Regards

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Sanu Krishnan
Sent: Monday, July 11, 2011 12:48 PM
To: materials-welding@googlegroups.com
Subject: [MW:11664] Poduction impact test

 

Dear experts,

       

  Is it Production imact test required for LTCS,upto -50degree C.Already PQR Test qualified in -50 degree C?

--

SANU.K.NAIR

QC INSPECTOR

DAEWOO E & C

ABUDHABI

Ph: 0507464738

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...