This is required during scraping the pipeline by the inspection instrument scraper / Calliper Run.
Regards,
Sohaib
From: limesh M <limesh78@gmail.com>
To: Materials & Welding <materials-welding@googlegroups.com>
Sent: Thu, May 12, 2011 8:02:32 AM
Subject: [MW:11038] pup piece in every 1 km
Dear All,
Why some client specification requires 6 m pipe pup piece in every 1 km pipeline?
Regards,
Limesh
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment