Dear all,

as per table 4.5 essential variables..
in base metal, it says to refer table 4.8.
In table 4.8 it says about only group number.
if group number changes from one which is not qualified require
requalification.. ok.
My question is..
Its doesn't says about M.number. so m.no changes is not required
requalification of wps.
can we go with same WPS if g.no mets?
The above said is right or wrong..
clear me.

Reagrds
Srinivas

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...