Wednesday, April 13, 2011

RE: [MW:10657] hydro testing of Pipelines

NO MORE THAN 0.85 BAR…mathematically

 

regards

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of SOHAIB GHNAIMAT
Sent: Tuesday, April 12, 2011 9:13 PM
To: materials-welding@googlegroups.com
Subject: [MW:10655] hydro testing of Pipelines

 

 

 


Team,

 

We have just completed the hydro test for 66" underground Pipeline the temperature at the begining of the test / Holding time was 13 Deg C. and after 14 hrs of the holding period ( 24 hrs ) the temperature was 24 deg C.

 

what will be the change in pressure ?

 

Regards,

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...