Monday, March 14, 2011

Re: [MW:10340] regarding using PQR & WPS

Hi,
Your existing PQR used 2 process and now you want to use only on eprocess (GTAW). You should prepare another WPS from the same PQR.

On Sun, Mar 13, 2011 at 5:37 PM, nadakuditi kiran kumar <kinnu78@gmail.com> wrote:
dear experts,

one of our client has approved a PQR qualified with the base metal is P5B to P5B.purging and Pre heat also done, having O.D.-4'',
thickness 14mm,process for root,hot pas,filler pass1 with GTAW,remaining filler pass & final with SMAW 
my question is 
we have same material & pipe dia  5" dia pipe,6.55 thickness,with only GTAW process only.now i can use that WPS where SMAW is also there.or i have to prepare another WPS with same PQR.

so please experts give valuable advice

thanks & regards
have a good day

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
suresh

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34874] ASME IX, groove weld during WQT limits for Fillet Weld production

Hi David,  There are two points in WQT. 1. Thickness of Base Metal -T 2. Thickness of Weld Metal -t When you use a combination of two proces...