Dear PSP..
 
Welding machines calibration will directly releated to heat input -control measure.. Hence machine calibration is required to ensure the display of current & voltage.
 
br,
 
msms

On Tue, Jan 18, 2011 at 12:58 PM, prashant pansare <prashantpan_99@yahoo.co.in> wrote:
Dear all,
Why we need to have calibration certificates of welding machines prior to start of fabrication activity?
As we can qualify WPS without the same.
Pl. reply.
Thanks & Regds,
PSP

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...