Dear Sir,

In the past it was not required to calibrate your welding equipment
but it was the responsibility of a manufacturer to execute such. So
manufacturers with comprehensive quality requirements or who are
welding critical materials and want to be sure the equipment delivers
the chosen parameters did perform this already for many years. Today
more and more specifications require calibration of equipment on a
annual base, this is not only for actual production but also for WPS
qualification.
For example when your production facility must be approved according
to ISO 3834 (quality assurance of production process) this is one of
the requirements.
As already mentioned by msms you need to ensure parameters shown on
the displays are correct in order to guarantee proper heat input.

Best Regards,

Herman Pieper

On 18 jan, 08:28, prashant pansare <prashantpan...@yahoo.co.in> wrote:
> Dear all,
> Why we need to have calibration certificates of welding machines prior to start of fabrication activity?
> As we can qualify WPS without the same.
> Pl. reply.
> Thanks & Regds,
> PSP

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...