Monday, December 13, 2010

RE: [MW:8720] Alloy Steel

Limesh,
 
Your reply is quite appropriate, except for some suggested points for improvement.Well fabrication practices are not really rocket sciences.However depending on the ambient temperature typically 35-40 deg C in warm climate and 10-15 deg C, in the shop floor(in a cold climate) and subzero in the outside, the fabrication practices may differ. However some extra precautions always help in the long run.
 
Thanks.
 
Pradip Goswami,P.Eng.,IWE.
Welding & Metallurgical Specialist & Consultant
Email-pgoswami@sympatico.ca,
 


From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of limesh M
Sent: Monday, December 13, 2010 7:35 AM
To: materials-welding@googlegroups.com
Subject: Re: [MW:8718] Alloy Steel


Dear Vasu,

ASTM A 335 Gr.P11 is not dangerous compared to P22. We welded plenty of P11 and P22 heavy walled pipes in our work shop with GTAW+SAW&GTAW+SMAW .If your welder cannot complete the joint in a single stretch, fill 3 passes or 1/3 of the groove thickness whichever is greater before leaving the job (Recommended).  

Cover the entire circumference of the weld after 1/3 of the groove filled to avoid sudden cooling of the weld metal (recommended). Preheat the joint again as per the approved WPS before starting the welding again. -- The covering of the weld should be done after performing post-heating or hydrogen bakeout. API 934E- recomemndations for P11 &P12 steel is -"The DHT shall be performed at a minimum metal temperature of 570°F (300°C) for duration of one hour minimum"(typically for all thicknesses of hydrtreaters). If  the fabrication it is a pipework  the post-heating may be performed at the the typical interpass temperature (e.g 250deg C max for P11/P12 steel) but typically for 30 min max.

Carryout MPT, if client insists (recommended). --This is considered to be a good practices.Depending on the interruptions there could be occurrances of delayed cracking some time. 

Note:- If welding is done consistently using H4 SMAW electrode and H5 SAW wire+fluxes, the above requirements may be minimized..

Note: There was no post heat done by us during the fabrication of ASTM A 335 P11 thick walled pipes for medium pressure steam lines during interruption. But we covered the entire joint with thick insulation blanket. Even without MPT we have welded P11 joints nearly up to 63 mm thickness. No cracks observed in RT&UT and the hardness was with in the limit.Electric resistance heating we utilised only for P22 and for P11 we utilised propane gas torch.Client insisted us to do electric resistance heating for P11 material.But we got concession from our client by showing our past experience on this material and they approved our proposal for torch heating. This is my experience and the plant is still running without any problem. --For  a thickness as above electric resistance heating would provide uniform heating and cooling gradients, and the thermal stresses on the weld/HAZ would be less. Specially designed propare burners (giving wider coverage) could be good alternatives, but certainly not Oxy-Propane torches, which would generate only spot heating. See the extracts from AWS D-10.10 as a ageneral gudence.
 

 Relative Advantages and Disadvantages of Resistance   Heating. The relative advantages of resistance   heating are as follows:

(1) Standard heaters can accommodate a wide variety   of part sizes and geometrical configurations.

(2) Continuous and even heat can be maintained   throughout the welding operation (including during long   breaks) from preheat/interpass heating through to postheating   or PWHT.

(3) Temperature can be adjusted accurately and   quickly.

(4) Welders can work in relative comfort and do not   have to stop intermittently to raise preheat temperature.

(5) Non-uniform or gradient heat input can be obtained   easily, such as may be required for the top and   bottom halves of a pipe or where pipes are attached to   heavier sections such as valves.

The relative disadvantages are as follows: -

(1) Elements may burn out during a heat treatment.   The possibility of this occurring is greatly reduced if elements   are inspected/maintained before each use. 

 (2) Inadequate work practices may create the possibility   for a resistance element to short itself out to the   pipe, producing arcing spots

 

Relative Advantages and Disadvantages of   Flame Heating. The relative advantages of flame heating   for local heating of welds are low cost and portability.

The relative disadvantages of flame heating are as   follows:

(1) Minimal precision and repeatability. 

 (2) Minimal uniform temperature distribution.

(3) The great amount of operator skill it requires.

(4) Risk of damaging the material

 Regards,
 
Limesh
 

 
On Mon, Dec 13, 2010 at 2:54 PM, Prasad Joshi <surpras@gmail.com> wrote:
Dear all,
 
P11 is not a very crack-prone material. It all depends on the WPS and the profile of the joint. In my opinion, following points will govern in fairly deciding the requirement of any corrective actions:
 
a) If the WPS specifiies the Post-heating, the same is mandatory and needs to be carried out w/o any delay before cooling to the RT.
b) If the WPS is silent on this, then, it all depends on the rigidity of the weld-joint.
  • If the joint is very thick and large diameter, the joint is prone to cracking due to restraints and lower strength of the joint during heating/cooling. In this view, it is very dangerous to discontinue welding immediately after root pass.
  • The post-heating followed by slow cooling (wraping insulating cover over the heated part) will reduce the hydrogen cracking.
  • In my opinion, the welding of joint can be resumed after carrying out MPT of the filler pass
I hope this clarifies,
 
Regards,
 
Prasad Joshi
Linde Engineering India Ltd.
 
 
On Mon, Dec 13, 2010 at 12:50 PM, manpreet <manpreetsin88@rediffmail.com> wrote:
Hi,

If welding is stopped for some time (less than a hour), the weld shall be covered to insure slow colling and 100% MT shall be done before presuming welding,

if for linger periods, Preheat would be required.

Regards
Manpreet Singh
Welding Engineer





On Sat, 11 Dec 2010 09:58:28 +0530 Prakash Hegde wrote
>
Hi!
Post heating is to be carried for weld which is dicontinued /interupted for long time where the preheated temeperature of the weld and surrounding area(Base)is not reduced
You can post heat discontinued weld and later on even next day you can continue the unfinished weld
However it is always advisible to complete the critical metallurgy weld in one go only (Better not to interrupt) In case of power failure you can keep the weld under preheating temperature range till the power is restored
Regards
Hegde P.B.

>

>

From: srinivas rao <ksrvasu@gmail.com>
>To: materials-welding@googlegroups.com
>Sent: Fri, 10 December, 2010 8:54:28 PM
>Subject: [MW:8670] Alloy Steel
>

> Dear All,
>
>While welding of ASTM A335 Gr P11, what to do if welding was stopped after Root Pass ,Hot Pass and One Fill-Up done without completing the job? Can we do immediately Post Heating for the un-finished job and continue welding next day? or Should we cut and re-weld the joint?
>
>I have one more doubt... In the above situation what if welding and Pre-heating(coil heating) was stopped due to power failure for 2 to 3 hrs and the joint has to come to room temp. Should the joint be cut and re-welded?
>
>Regards,
>
>Vasu
>
>
>

--
>To post to this group, send email to materials-welding@googlegroups.com
>To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
>For more options, visit this group's bolg at http://materials-welding.blogspot.com/
>The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
>

>

--
>To post to this group, send email to materials-welding@googlegroups.com
>To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
>For more options, visit this group's bolg at http://materials-welding.blogspot.com/
>The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
>

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...