Re: [MW:8377] Hydrotesting Pressure gauge calibration

Dear Karthik :

I have a complicated situation with pressure gauge calibration period.

During calibration test, our gauge found to be showing wrong reading (below actual). And clients ask to re-test all spool pipe tested using the gauge.

My question, is that acceptable ? luckily there are only small number of spool to be re-tested, but I cant imagine if that happens to spools that already put in service.re

Just a share, but I appreciate any coments and advise.

Best Regards
Bonardo



From: Karthik <karthik6684@yahoo.com>
To: materials-welding@googlegroups.com
Sent: Thu, 25 November, 2010 2:13:24 PM
Subject: Re: [MW:8373] Hydrotesting Pressure gauge calibration

Hi,
Pressure gauge calibration time shall be in every 6 months as per the normal practice and various project specifications.

Thanks & Regards,

(Karthik)

Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282


--- On Thu, 11/25/10, Praveen Kumar <praveenkumar.sek@gmail.com> wrote:

From: Praveen Kumar <praveenkumar.sek@gmail.com>
Subject: [MW:8372] Hydrotesting Pressure gauge calibration
To: materials-welding@googlegroups.com
Date: Thursday, November 25, 2010, 1:22 PM

Dear All,

 

Can you pls Suggest as the Piping Hydrotesting Pressure gauge calibration period of time,

and also is there any code/stds governing for this.

 

 

 

Regards,

 

Praveen Kumar

Mechanical Engineer

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

 

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...