As per ASME sec. IX, The addition of position is a non essential variable, also change in position is supplementary variable. If your PQR doesn't have impact test, you may use the same WPS, You need not to go for a new PQR.
Hope you understand the summary.
M.Sivachidambaram
+919597165173
On Thu, Nov 11, 2010 at 3:05 PM, Zulfan <zulfan@insing.com> wrote:
Dear all,please advice in our PQR mentioning position 3G and our WPS stated 1Gis the WPS able to apply or need to run again PQR again?code ASME sec IXThankzul--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment