[MW:8282] ASME SEC-IX CONTINUITY REQUIREMENT

Dear All,
Can any one define how to go for continuity of the welders?
What are the criteria for continuity other than 6months qualification.
If a welder is qualified in SMAW process for Both Groove welding and CRO
and his qualification date has exceeded 2 years and he is continuously
welding for Groove welding but for more than he has not done overlay
welding. Is he qualified for Weld Overlay?

Thanking you,
Best regards,

Shadab

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...