This vessel is partly manufactured at shop & final assembly /
hydrotest carried at field.
My organization is having ASME U stamp certificate of authorization &
socpe covering
shop & field activities.
My question is while moving out semi finished vessel from shop to
field whether
Manufacturers Partial Data Report is required?
Field assembly & testing will be completed by same organization.
Experts / ASME Authorized Inspector's views are requested.