Skip to main content

[MW:7424] Re: Post Heating for Alloy Steel

Post Heating Post heating is used to minimize the potential for
hydrogen induced cracking (HIC).
For HIC to occur; the following variables must be present. a sensitive
microstructure, a sufficient level of hydrogen, or a high level of
stress (e.g., as a result of highly constrained connections).
In Ferritic steels, hydrogen embrittlement only occurs at temperatures
close to the ambient temperature. Therefore, it is possible to avoid
cracking in a susceptible microstructure by diffusing hydrogen from
the welded area before it cools.
After welding has been completed, the steel must not be allowed to
cool to room temperature; instead, it should be immediately heated
from the interpass temperature to the postheat temperature and held at
this temperature for some minimum amount of time. Although various
code and service requirements can dictate a variety of temperatures
and hold times, 450°F(230°C) is a common post heating temperature to
be maintained for 1hour per inch (25 mm) of thickness. Post heating is
not necessary for most applications. The need for post heating assumes
a potential hydrogen cracking problem exists due to a sensitive base
metal microstructure, high levels of hydrogen, and/or high stresses.
Post heating, however, may be a code requirement. For example, ASME
Section III and the National Board Inspection Code (NBIC) both have
such provisions. The Section III requirement for P-No.1 materials
is450 to 550°F (230 to 290°C) for a minimum of 2 hours, while the NBIC
requirement is 500 to 550°F (260 to290°C) for a minimum of 2 hours.
Furthermore, post heating is often required for critical repairs, such
as those defined under the Fracture Control Plan (FCP) for Non
redundant Members of the AASHTO/AWS D1.5Bridge Welding Code. The FCP
provision is 450 to 600°F (230 to 315°C) for "not less than one hour
for each inch(25 mm) of weld thickness, or two hours, whichever is
less."When it is essential that nothing go wrong, post heating can be
used as insurance against hydrogen cracking. However, when the causes
of hydrogen cracking are not present, post heating is not necessary,
and unjustifiable costs may result if it is done.

Jaspal Singh, CWI-AWS, CSWIP-3.1
Quality Assurance
Process Equipment Division
ISGEC, Yamuna Nagar, Haryana -135001
Phone: 911732307251
Ext: 251 Mb: +91 9996624244

On Oct 7, 12:36 pm, muthusrinivasan muthuselvam <msm...@gmail.com>
wrote:
> Hydrogen embrittlement occurs when the weldment temperature is below 300 C
> not close to ambient temperature.
>
> br,
> msms
>
> On Wed, Oct 6, 2010 at 7:35 PM, Jignesh Desai
> <jignesh.desai....@gmail.com>wrote:
>
>
>
> > In ferritic steels, hydrogen embrittlement only occurs at temperatures
> > close to the ambient temperature. Therefore, it is possible to avoid
> > cracking in a susceptible microstructure by diffusing hydrogen from the
> > welded area before it cools. After welding has been completed, the steel
> > must not be allowed to cool to room temperature; instead, it should be
> > immediately *heated from the interpass temperature to the post heat
> > temperature *and held at this temperature for some minimum amount of time.
>
> > Also did you see UOP Spec 8-12-6, para 2.4(a) - Fabrication of piping?,
> > where UOP asked for post heating of carbon steel? It may be carried out for
> > some case of CS where thickness>50.0 mm). I am sure this spec. must be part
> > of your project.
>
> > On Wed, Oct 6, 2010 at 11:47 AM, muthusrinivasan muthuselvam <
> > msm...@gmail.com> wrote:
>
> >> Mr.Senthil..
>
> >> The main purpose of doing immediate PWHT without post heating is to avoid
> >> hydrogen induced cracking.. To my knowledge there is no code requirement or
> >> specification mentioning about the time after which you can do the PWHT.
>
> >> But please note that delaying the PWHT after welding will improve the
> >> condition for hydrogen induced cold cracking. So the PWHT has to be carrried
> >> out immediately after completion of welding.
>
> >> best regards,
>
> >> M.S.Muthu selvam.
>
> >>   On Tue, Oct 5, 2010 at 10:42 PM, senthil raja <
> >> senthilrajabara...@gmail.com> wrote:
>
> >>> Hi,
>
> >>>  I m Senthil working in L&T. I m presently in MRPL project,
> >>> Mangalore. In our client(EIL) specification it is given that post
> >>> heating shall be carried out for the alloy steels (Cr-Mo) where PWHT
> >>> cannot be carried out immediately.
>
> >>> I need to know what is the time limit within which PWHT shall be
> >>> carried out without post heating. What is the standard or code which
> >>> can be reffered for this.
>
> >>> Kindly share your experience sirs & friends,
>
> >>> regards,
> >>> Senthil Raja.
>
> >>> --
> >>> To post to this group, send email to materials-welding@googlegroups.com
> >>> To unsubscribe from this group, send email to
> >>> materials-welding-unsubscribe@googlegroups.com
> >>> For more options, visit this group's bolg at
> >>>http://materials-welding.blogspot.com/
> >>> The views expressed/exchnaged in this group are members personel views
> >>> and meant for educational purposes only, Users must take their own decisions
> >>> w.r.t. applicable code/standard/contract documents.
>
> >> --
> >> To post to this group, send email to materials-welding@googlegroups.com
> >> To unsubscribe from this group, send email to
> >> materials-welding-unsubscribe@googlegroups.com
> >> For more options, visit this group's bolg at
> >>http://materials-welding.blogspot.com/
> >> The views expressed/exchnaged in this group are members personel views and
> >> meant for educational purposes only, Users must take their own decisions
> >> w.r.t. applicable code/standard/contract documents.
>
> > --
> > To post to this group, send email to materials-welding@googlegroups.com
> > To unsubscribe from this group, send email to
> > materials-welding-unsubscribe@googlegroups.com
> > For more options, visit this group's bolg at
> >http://materials-welding.blogspot.com/
> > The views expressed/exchnaged in this group are members personel views and
> > meant for educational purposes only, Users must take their own decisions
> > w.r.t. applicable code/standard/contract documents.- Hide quoted text -
>
> - Show quoted text -

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

Comments

Popular posts from this blog

Re: [MW:34105] SA266 GR4N 4 Cycle SPWHT

Hi,  You are correct, Minimum refers to the one cycle for which this part will expose until final work shop PWHT. hence mill test certificate shall include this.  Max. SPWHT, refers to additional cycles of heat treatment that are reserved for future repairs during equipment lifetime.  Again, these simulated no. Of cycles shall be specified in MTC.  The idea is we need to make sure that steel mechanical properties are not compromised upon exposure to multiple repairs (i e 4 cycles in your case).  One could say, if steel is subjected to 4 cycles and is ok, then it should by defacto be good for one cycle, yet, this is wrong assumption cause mechanical problems and microstructure of materials varies accordingly based on no. Of cycles for which material will expose. This is apparent in alloy steel and especially for impact test values as an example.  In your case, this forged CS with properties before PWHT can be understood to be " as forged" condition (i.e. Wit...

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...