[MW:7369] Interpass temperature during PQR

Dear All,
 
Design code - ASME B31.3
Welding Code - ASME SEC IX
Client Spec Says - Interpass temperature to be monitored and measured during welding.
 
During PQR I observed that run out length of one electrode was around 75-100 mm.So the welder couldn't complete the joint in a single stretch.In this condition, should I take the interpass temperature before using the second electrode from the first bead end?
 
More over,the welder can complete the root pass by using three electrodes/filler wire.In this condition should I measure and record three interpass temperatures?ie, first temperature,ambient(starting),second temperature ,during starting of second electrode,Third temperature  during staring of third elecrode.
 
Or one temperature is enough just before starting hot pass?
 
 
Regards,
 
Limesh78
 
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...