Dear All
What is the purpose of using WPS with multiple PQRs. What all variables can be changed while documenting a new WPS supported by multiple PQRs.
For eg: I have two PQRs:
Applicable Code: AWS D1.1
1) Root & Hot pass - GTAW
Filler & Capping - SMAW
2) Root and Hot pass - GTAW
Filler & Capping - FCAW
Whether I can document a new WPS with Root & Hot pass - GTAW, Filler & Capping - SMAW; supported by the above PQRs.
Thanks and Regards
Harikrishnan N S
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Subscribe to:
Post Comments (Atom)
[MW:34820] RE: 34813] Clarification in Rate of heating and cooling.
Hello, Please see the response below. Regards. P. Goswami, P. Eng, IWE. From: materials-welding@googlegroups.com <materials-weld...
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...