Dear All
What is the purpose of using WPS with multiple PQRs. What all variables can be changed while documenting a new WPS supported by multiple PQRs.
For eg: I have two PQRs:
Applicable Code: AWS D1.1
1) Root & Hot pass - GTAW
Filler & Capping - SMAW
2) Root and Hot pass - GTAW
Filler & Capping - FCAW
Whether I can document a new WPS with Root & Hot pass - GTAW, Filler & Capping - SMAW; supported by the above PQRs.
Thanks and Regards
Harikrishnan N S
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Subscribe to:
Post Comments (Atom)
[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point
Dear Experts. If anyone having presentation of WPS,PQR and WPQ as per ASME SEC.IX in power point then please share . Regards Sanja...
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...
No comments:
Post a Comment