[MW:7026] PWHT and Welding requirement of Carbon steel to P22

Dear All,

Kindly suggest your valuable suggestions for following:

1.       Welding consumables for welding of P22 to Carbon steel and why?

2.       PWHT requirement.

3.       The wall thickness of tubes and pipe is from 10mm to 35mm

 

Regards

 

Naveen Kumar

 

 

No comments:

Re: [MW:34874] ASME IX, groove weld during WQT limits for Fillet Weld production

Hi David,  There are two points in WQT. 1. Thickness of Base Metal -T 2. Thickness of Weld Metal -t When you use a combination of two proces...