with refrence to bashir mail please be advice that the required test depends on the construction code
note: 9 cr and CS is not recommended to be welded together

 

Date: Sat, 19 Jun 2010 16:40:34 +0400
Subject: Re: [MW:5658] Welding Procedure
From: harishkannepalli@gmail.com
To: materials-welding@googlegroups.com

Dear Bhatti,
 What is code for Procedure? What is the job? Normally you require tensile,bend,charpy impact(conditional) and macroexamination.

2010/6/17 Bhatti BM (Bashir) at Aera <BMBhatti@aeraenergy.com>

 

 

 

Folks,

We doing  Mockup procedure before actual welding, what type tests are required to qualify the welding procedure

 

 I was looking for welding procedures for and filler metals

 CS A-106-B and 2 ¼ Cr ,

CS A-106-B and 410

CS A-106-B and 13 Cr

CS A-106-B and 9CR

 

Thanks , Bashbhat

 


--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
K Harish Kumar

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.


Your E-mail and More On-the-Go. Get Windows Live Hotmail Free. Sign up now.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...