Tuesday, June 8, 2010

Re: [MW:5437] API 650 requirements

and revised too in API 653 inspection, alteration and rerating of tank.
 
Agustin


De: kamal nathan <kamalihi@gmail.com>
Para: materials-welding@googlegroups.com
Enviado: lun, junio 7, 2010 1:31:51 AM
Asunto: Re: [MW:5420] API 650 requirements

API fully refers to ASME IX for WPS,PQR,WQT  & ASME V for NDT.
Third party services depends on the purchaser only,
kamal

On Sun, Jun 6, 2010 at 8:33 PM, Sandeep Kp <sandeepkp99@yahoo.com> wrote:
Dear all,
what is the requirements of API 650 jobs,
About WPS,PQR,WQT,NDT and thired party inspection requirements.
 
 
 
With Regards,
Sandeep.k.p
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

 

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...