Monday, May 24, 2010

Re: [MW:5220] A860WPHY

Hi ,
        Your TPIA is correct you need to have a PQR ,Normally these kind of fitting order with Test Ring with same heat Number for any PQR qualification.If you not have any other option raise varience and get approved from your client.
 
Vaithiyanathan

On Sat, May 22, 2010 at 11:57 AM, Rajpal Dhillon <rajpal.bantaa@gmail.com> wrote:
Dear Members,
We are to weld the A860 WPHY 65 Flow Tee to A333 Gr6 pipe.Our TPIA is asking for a separate PQR for this.We already have a PQR fpr A333 Gr6. Our main concern is if        we onduct a PQR fpr A860WPHY TO A333Gr6 we will loose one Flow Tee which we have imported from ITALY.To get a new Floe tee it will take minimum three months which we can not afford at this point of time. Is there any way out.
 
 
Rajpal Singh Dhillon

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
With Best Regards

B.Vaithiyanathan

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...