Friday, May 21, 2010

Re: [MW:5213] NDT after PWHT

Mmmmmmm sorry I should have said that the material is SA-516-70, this is ferritic steel welded with E7018, so I believe UHA-33b and UHA-33a do not apply? 
Luis Albanés

--- El jue 20-may-10, francis.lobo@indiatimes.com <francis.lobo@indiatimes.com> escribió:

De: francis.lobo@indiatimes.com <francis.lobo@indiatimes.com>
Asunto: Re: [MW:5201] NDT after PWHT
A: materials-welding@googlegroups.com
Fecha: jueves, 20 de mayo de 2010, 23:13

Dear Friends,
We need to check all requirements in line with code specific to the item . Certain codes do specify NDT after PWHT . Certain client specifications specify the NDT requirements after PWHT . so do not conclude  requirements  in general.You may refer this in BS 5500 for pressure vessels or B31.3 for piping
 Regards,

----- Original Message -----
From: dlsltd@telus.net
To: materials-welding@googlegroups.com
Sent: Thu, 20 May 2010 23:41:40 +0530 (IST)
Subject: Re: [MW:5199] NDT after PWHT








 

 

I don't believe there is any requirements, but
on  P5-B materials, it is a common practice as cracks have been known
to form after 24 hours on these materials. I have heard of some materials
on "Hold" pending another RT after the initial test after 7 Days.

 

I have just completed PWHT on ASME 1 piping and
there is no requirement on P1 material for additional RT after cool
down.


----- Original Message -----



Sent: Thursday, May 20, 2010 6:30
AM

Subject: [MW:5198] NDT after PWHT








Dear friends

We just finished PWHT in an LPG sphere acording to ASME VIII
section I, and I can´t find in the code the part that obligues to Xray
after this treatment, any one has experience with this? where does
ASME VIII say it has to be done?

Thank you

Luis Albanés

 
--
To post to this group, send email to materials-welding@googlegroups.com
To
unsubscribe from this group, send email to
materials-welding-unsubscribe@googlegroups.com
For more options, visit this
group's bolg at http://materials-welding.blogspot.com/
The
views expressed/exchnaged in this group are members personel views and meant
for educational purposes only, Users must take their own decisions w.r.t.
applicable code/standard/contract documents.




--

To post to this group, send email to materials-welding@googlegroups.com

To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com

For more options, visit this group's bolg at http://materials-welding.blogspot.com/

The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Click for exclusive coverage on the New Bajaj Pulsar 220 the fastest Indian bike
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...