[MW:5161] UT scanning of Ball v/v type B8

Dear all
this is a case of UT scanning of Ball v/v type B8.

procedure says- The search unit shall be positioned for maximum response using holes at 1/4, 2/4 and 3/4.
The primary reference level shall be based on 75% of full screen height response.
but company says- Since the inspection is performed from one side only 2 DAC shall be done. The first one as suggested in the procedure and the second one starting at ¾, 6/4 and 7/4. This is to obtain a reference for full skip inspection.

can somebody give me some guidance on it?

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...