Re: [MW:4687] Difference between pipes and tubes

Pipes----- Mass Transfer only(generally---ID controlled)
Tubes----- Mass And Heat Transfer ( generally--od and thick is controlled)
do not use STT for hot and fill pass
KGP

On Sat, Apr 3, 2010 at 3:06 PM, Gulam kader <armvasi@gmail.com> wrote:
Hai all,

1.Please somebody can explain difference between pipes and tubes with some references.

2. In our project continuously getting repair ( Cold lap) in hot and fill pass. can u suggest some good way to avoid or rectify this.

material Used - CS dia 68,64 and 60"

Process : Root - STT, Other - FCAW shielding by gas ( Ar80%, CO2 20%- 48 CFH)

Filler metal for FCAW : A5.20 E71T-9M

Expecting reply as soon as possible.

Regards,

Meera

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...