Thursday, February 11, 2010

Re: [MW:4286] DRAIN POINT_DELUGE PIPING

Yes, not process draing but for hydrotest, high and low points

Regards



On Thu, 11 Feb 2010 10:48:56 +0530 wrote
>Dear Sirs,Do we require to give drain points in Deluge piping(sprinkler system/fire fighting)?If yes, at what intervals on the pipe its to be given & which is the code pertaining to this ?

--
Regards
AAKARSH PP






--
>
To post to this group, send email to materials-welding@googlegroups.com
>
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
>
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
>
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
>


Chandra Bhusan Tripathi
23 Beckett Circle
Perth, WA
Australia
M +61422812970
H +61862012197

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34820] RE: 34813] Clarification in Rate of heating and cooling.

Hello,   Please see the response below.   Regards.   P. Goswami, P. Eng, IWE.   From: materials-welding@googlegroups.com <materials-weld...