Please clarify meanings of below clauses with examples.
 
1) whether new PQR  has to be performed if  there is change in GROVE TYPE from V to U During production OR only revising the WPS by incorporating the changed GROVE TYPE will be enough.
 
2) Whether gas purging used during GTAW welding can be consider as BACKING.
 
3) Please clarify the meaning of paragraph  - QW - 403.5( Only for paragraph below point C) with example.
 
4) Please clarify the meaning of paragraph  - QW - 202.4b(2)with example.
 
5) whether change of electrode clasification  under same SFA e.g. change of elctrode from E7018  to E7018-1 or VICE VERSA requires qualification of new PQR.
 
6) Please clarify the meaning of paragraph  - QW - 404.12 & 404.33 with example.
 
 
Thanks & Regards
 
Asad Azmi

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...