We are constructing tank as per API 650 & tell tale hole is required for reinforcing plate for all opening as per code.
But how about doubler plates and supports which will be permanent attachments on shell. I know tell tale hole is not required for leak test but at least vent hole is reqd as per good engg practice.But API 650 is silent on this issue.
Please suggest
Regards

Bharat B. Gole





http://windows.microsoft.com/shop Find the right PC for you.
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34820] RE: 34813] Clarification in Rate of heating and cooling.

Hello,   Please see the response below.   Regards.   P. Goswami, P. Eng, IWE.   From: materials-welding@googlegroups.com <materials-weld...